DST S.A.
  • About Us
    • Who we are
    • History
    • Financial information
    • Certifications
    • Social Responsibility and Environment
    • Recruitment
    • MANAGEMENT POLICY
  • Activity Areas
  • Portfolio
    • All the areas
    • Construction
    • Infrastructures
    • Water, Environment and Energy
  • Works in progress
    • All the areas
    • Construction
    • Infrastructures
    • Water, environment and energy
  • Contact Us
  • en
    • English (US)
    • Português
    • Français
    • Español
Back
Palmeira - Braga
Palmeira WWTP
Infraestruturas Ambientais
Data Sheet
The aim of this project was the design / construction, pre-start and start-up of the Palmeira WWTP, whose treatment process includes: preliminary treatment (sieving, sedimentation and degreasing). In the solid phase treatment, the mechanical thickening and dewatering of the sludge by band filter was included. Also included was the treatment of odours produced in the facility. The contract also included the outfall for discharge of treated effluent into in the receiving environment. While the work was carried out, the maintenance of the existing pond and aeration system was ensured, in order to allow the treatment of the effluent. Upon completion of the construction of the WWTP, the ponds and the remaining buildings were demolished / upgraded.
The main data for the WWTP, for the project horizon, was: equivalent population of 32,000 inhabitants and average flow of 6,560 m3 / day.
+ learn more
Client
AGERE- Empresa de Águas, Efluentes e Resíduos de Braga, E.M.
Time of execution
10 months
Request Technical Data Sheet
Back
Palmeira - Braga
Palmeira WWTP
Infraestruturas Ambientais
/
Data Sheet
The aim of this project was the design / construction, pre-start and start-up of the Palmeira WWTP, whose treatment process includes: preliminary treatment (sieving, sedimentation and degreasing). In the solid phase treatment, the mechanical thickening and dewatering of the sludge by band filter was included. Also included was the treatment of odours produced in the facility. The contract also included the outfall for discharge of treated effluent into in the receiving environment. While the work was carried out, the maintenance of the existing pond and aeration system was ensured, in order to allow the treatment of the effluent. Upon completion of the construction of the WWTP, the ponds and the remaining buildings were demolished / upgraded.
The main data for the WWTP, for the project horizon, was: equivalent population of 32,000 inhabitants and average flow of 6,560 m3 / day.
+ learn more
Client
AGERE- Empresa de Águas, Efluentes e Resíduos de Braga, E.M.
Time of execution
10 months

TECHNICAL SHEET

The aim of this project was the design / construction, pre-start and start-up of the Palmeira WWTP, whose treatment process includes: preliminary treatment (sieving, sedimentation and degreasing). In the solid phase treatment, the mechanical thickening and dewatering of the sludge by band filter was included. Also included was the treatment of odours produced in the facility. The contract also included the outfall for discharge of treated effluent into in the receiving environment. While the work was carried out, the maintenance of the existing pond and aeration system was ensured, in order to allow the treatment of the effluent. Upon completion of the construction of the WWTP, the ponds and the remaining buildings were demolished / upgraded.
The main data for the WWTP, for the project horizon, was: equivalent population of 32,000 inhabitants and average flow of 6,560 m3 / day.
Cliente
AGERE- Empresa de Águas, Efluentes e Resíduos de Braga, E.M.
Prazo de Execução
10 months
Technical Sheet Request

Call us

or

Write us

cofinacied by  
SetWidth480-compete2020.png
SetWidth480-portugal2020.png
SetWidth480-UE2020.png
Projetos Financiados ID&T
Baterias 2030
ReNew
New Generation Storage
 
SetWidth480-prr.png
SetWidth480-logo-RP-branco-Prancheta-1.png
SetWidth480-ue-next.png
PRR Portugal
R2UTechnologies | modular system
Follow us on social networks
Construction charter
DOMINGOS DA SILVA TEIXEIRA, S.A. 2846 - PUB
© 2022 dstgroup. All rights reserved. Privacy policy. Website developed by innovationpoint