Ruães
WWTP Ruães
Infraestruturas Ambientais
Data Sheet
This project involved the design / construction, pre-start and start-up of the Ruães WWTP, where the treatment process includes: preliminary treatment (sieving, sedimentation and degreasing) and tertiary treatment (removal of Nitrogen and Phosphorus) through suspended biomass system at low load. In the solid phase treatment, the mechanical thickening and dewatering of the sludge by band filter was included. The treatment of odours produced in the installation, by biological means was also included. The contract also included the outfall for discharge of treated effluent into in the receiving environment.
While the work was carried out, the maintenance of the existing pond and aeration system was ensured, in order to allow the treatment of the effluent. Upon completion of the construction of the WWTP, the ponds and the remaining buildings were demolished / upgraded.
The main data for the WWTP, for the project horizon, was: equivalent population of 20,000 inhabitants, average flow of 3,000 m3 / day and peak flow of 260 m3 / h.
+ learn more
Client
AGERE- Empresa de Águas, Efluentes e Resíduos de Braga, E.M.
Time of execution
480 days
Request Technical Data Sheet
Back
Ruães
WWTP Ruães
Infraestruturas Ambientais
/
Data Sheet
This project involved the design / construction, pre-start and start-up of the Ruães WWTP, where the treatment process includes: preliminary treatment (sieving, sedimentation and degreasing) and tertiary treatment (removal of Nitrogen and Phosphorus) through suspended biomass system at low load. In the solid phase treatment, the mechanical thickening and dewatering of the sludge by band filter was included. The treatment of odours produced in the installation, by biological means was also included. The contract also included the outfall for discharge of treated effluent into in the receiving environment.
While the work was carried out, the maintenance of the existing pond and aeration system was ensured, in order to allow the treatment of the effluent. Upon completion of the construction of the WWTP, the ponds and the remaining buildings were demolished / upgraded.
The main data for the WWTP, for the project horizon, was: equivalent population of 20,000 inhabitants, average flow of 3,000 m3 / day and peak flow of 260 m3 / h.
+ learn more
Client
AGERE- Empresa de Águas, Efluentes e Resíduos de Braga, E.M.
Time of execution
480 days

TECHNICAL SHEET

This project involved the design / construction, pre-start and start-up of the Ruães WWTP, where the treatment process includes: preliminary treatment (sieving, sedimentation and degreasing) and tertiary treatment (removal of Nitrogen and Phosphorus) through suspended biomass system at low load. In the solid phase treatment, the mechanical thickening and dewatering of the sludge by band filter was included. The treatment of odours produced in the installation, by biological means was also included. The contract also included the outfall for discharge of treated effluent into in the receiving environment.
While the work was carried out, the maintenance of the existing pond and aeration system was ensured, in order to allow the treatment of the effluent. Upon completion of the construction of the WWTP, the ponds and the remaining buildings were demolished / upgraded.
The main data for the WWTP, for the project horizon, was: equivalent population of 20,000 inhabitants, average flow of 3,000 m3 / day and peak flow of 260 m3 / h.
Cliente
AGERE- Empresa de Águas, Efluentes e Resíduos de Braga, E.M.
Prazo de Execução
480 days
Technical Sheet Request

Call us

or

Write us

cofinacied by  
SetWidth480-compete2020.png
SetWidth480-portugal2020.png
SetWidth480-UE2020.png
Projetos Financiados ID&T
Baterias 2030
ReNew
New Generation Storage
 
SetWidth480-prr.png
SetWidth480-logo-RP-branco-Prancheta-1.png
SetWidth480-ue-next.png
PRR Portugal
R2UTechnologies | modular system
Follow us on social networks
Construction charter
DOMINGOS DA SILVA TEIXEIRA, S.A. 2846 - PUB
© 2022 dstgroup. All rights reserved. Privacy policy. Website developed by innovationpoint