Lousada
Sousa WWTP
Infraestruturas Ambientais
Data Sheet
The purpose of this project was the design / construction, pre-start and start-up of the Sousa WWTP. The treatment scheme for this WWTP is based on a biological wastewater treatment with activated-sludge process operated in a conventional aeration system, carried out through two bioreactors with the configuration of an oxidation ditch. There are two treatment phases: liquid phase and solid phase. The main data for the WWTP, for the project horizon, was: equivalent population of 90,000 inhabitants and average flow of 13,855 m3 / day.
+ learn more
Client
Águas do Norte
Time of execution
42 months
Request Technical Data Sheet
Back
Lousada
Sousa WWTP
Infraestruturas Ambientais
/
Data Sheet
The purpose of this project was the design / construction, pre-start and start-up of the Sousa WWTP. The treatment scheme for this WWTP is based on a biological wastewater treatment with activated-sludge process operated in a conventional aeration system, carried out through two bioreactors with the configuration of an oxidation ditch. There are two treatment phases: liquid phase and solid phase. The main data for the WWTP, for the project horizon, was: equivalent population of 90,000 inhabitants and average flow of 13,855 m3 / day.
+ learn more
Client
Águas do Norte
Time of execution
42 months

TECHNICAL SHEET

The purpose of this project was the design / construction, pre-start and start-up of the Sousa WWTP. The treatment scheme for this WWTP is based on a biological wastewater treatment with activated-sludge process operated in a conventional aeration system, carried out through two bioreactors with the configuration of an oxidation ditch. There are two treatment phases: liquid phase and solid phase. The main data for the WWTP, for the project horizon, was: equivalent population of 90,000 inhabitants and average flow of 13,855 m3 / day.
Cliente
Águas do Norte
Prazo de Execução
42 months
Technical Sheet Request

Call us

or

Write us

cofinacied by  
SetWidth480-compete2020.png
SetWidth480-portugal2020.png
SetWidth480-UE2020.png
Projetos Financiados ID&T
Baterias 2030
ReNew
New Generation Storage
 
SetWidth480-prr.png
SetWidth480-logo-RP-branco-Prancheta-1.png
SetWidth480-ue-next.png
PRR Portugal
R2UTechnologies | modular system
Follow us on social networks
Construction charter
DOMINGOS DA SILVA TEIXEIRA, S.A. 2846 - PUB
© 2022 dstgroup. All rights reserved. Privacy policy. Website developed by innovationpoint